A standard shelter leaves the factory in 10–14 weeks and a bespoke one in 16–22 weeks, before ocean transit of 5–40 days depending on lane. Production accounts for only 40–60% of that calendar. Drawing approval, mill runs, coating batches and shipping sit outside it, so the delivery date must be built backwards from site handover.
A transport officer who orders in March for a June opening is not buying a shelter. They are buying a conversation about air freight, a temporary stop, and an advertising contract that starts without a screen.
The mistake is arithmetic, not intent. Buyers add a quoted production period to a shipping estimate and call the total a lead time. Suppliers quote the part of the calendar they control. Between those two figures sit the approval cycles, the mill runs, the galvanising queue, the vessel cut-off and the customs broker — and that gap is where opening dates are lost.
This is a schedule guide for the person who has to sign the delivery date. It separates the weeks a factory owns from the weeks you own, and turns both into tender language.
What must you fix before anyone can quote a lead time?
Eight inputs fix the number, and a supplier quoting without them is quoting an industry average. State the model and module length, the drawing approval route, quantity per tranche, finish, glazing, power and CMS specification, incoterm and destination port, and the site handover date. The last two decide more of the calendar than the first six.
Input | What to state | Effect on the calendar |
Model and module length | Standard 4 m, 6 m or 8 m module, or a length outside the range | A standard module reuses existing cutting plans and jigs; a new length re-enters design and fabrication set-up |
Drawing approval route | Who signs — your engineer, a local structural engineer, a planning authority | Each approval cycle costs 1–3 weeks; a two-stage route costs two cycles |
Quantity per tranche | Units per call-off and per year, with tranche dates | A 120-unit framework called off ten at a time runs on a different schedule from a single 120-unit order |
Finish | Stock RAL, non-stock RAL, PVDF, anodised | A non-stock colour waits for a coating batch, not for a machine |
Glazing | Tempered 8/10/12 mm to EN 12150-1, laminated, polycarbonate | Tempered panels are cut before toughening; a late change restarts the furnace run |
Power and CMS | Mains, solar array size, screen size, CMS platform and interface | Non-stock LED modules and controllers carry 4–6 week procurement windows of their own |
Incoterm and port | Ex works, FOB, CIF, DAP or DDP, with the named port | Decides where your responsibility for delay starts |
Site handover date | The date the stop must be operational, per site | The only fixed point in the whole calculation |
【YEROO DATA NEEDED: standard and bespoke lead times by model — design, production, factory acceptance testing and packing — expressed in working days, and the effect of order band (10 / 100 / 500 units) on each】.
The handover date is the anchor. Work backwards: subtract installation and commissioning, subtract import clearance and inland haulage, subtract ocean transit, subtract packing, testing and production. What remains is the date the drawings must be approved — and it is almost always earlier than the buyer expected. An enquiry that says "required delivery: as soon as possible" cannot be answered with a date, only with a hope.

What actually happens inside the lead time?
Twelve stages sit between order and site, and the factory controls six of them. Design approval, material procurement, fabrication, galvanising, coating, glazing and testing belong to production. The rest belongs to your forwarder, your customs broker and your own site. A twelve-week promise that ignores the last four stages is a fabrication promise, not a delivery promise.
Durations below are indicative global ranges for the industry, not YEROO's committed schedule. Use them to interrogate a quotation, and require the bidder to replace every row with a dated commitment.
# | Stage | Controlled by | Indicative duration | What stalls it |
1 | Design freeze and drawing pre-approval | Buyer and supplier | 1–3 weeks per cycle | Unresolved foundation interface, late structural sign-off |
2 | First-article or prototype (if required) | Factory | 2–5 weeks | Ordered after the drawings rather than with them |
3 | Material procurement — steel, aluminium extrusion, glass, LED, drivers | Factory | 2–5 weeks | New extrusion die, non-stock LED batch, coil allocation |
4 | Fabrication and welding to EN 1090-2 EXC2 | Factory | 1–3 weeks per 10-unit block | Rework from post-approval design changes |
5 | Hot-dip galvanising to ISO 1461:2022 | Sub-supplier | 5–10 working days | Kettle queue at peak season; members over bath length |
6 | Powder coating or PVDF, 60–80 μm dry film | Factory or sub-supplier | 3–7 days including cure | Colour batch scheduling |
7 | Glazing, electrical fit-out, CMS load and configuration | Factory | 1–2 weeks | Glass breakage in handling; controller firmware |
8 | Factory acceptance test | Joint | 1–3 days plus witness notice | Your inspector's availability |
9 | Packing and container loading | Factory | 3–5 days | Heat-treated timber crating to ISPM 15 |
10 | Inland haulage and export clearance | Forwarder | 3–7 days | Port congestion, vessel cut-off, HS code query |
11 | Ocean transit | Carrier | 5–40 days by lane | Blank sailing, rollover to the next vessel |
12 | Import clearance and inland delivery to site | Buyer | 1–3 weeks | Missing certificate of origin or ISPM 15 mark |
Three clocks run in parallel, and only one of them is a factory clock. The approval clock starts when drawings are issued and stops when they are signed. The shipping clock starts at booking, not at loading, and a 40 ft high-cube under ISO 668:2020 still has to be found, positioned and cleared before it can be stuffed. The production clock is the one quoted in the sales email, and it is the shortest of the three.
Indicative ocean transit ranges from South China: 5–10 days to South-East Asia, 16–22 days to Australia, 18–25 days to the Gulf, 25–32 days to the Mediterranean and 30–40 days to North Europe. Add two weeks of buffer for a first shipment on a new lane, because the first booking is always the one that rolls.
Why do lead times slip — and which slips are the buyer's own?
Most slippage is created before fabrication starts, and most of it is buyer-side. Late drawing approval, a foundation detail changed after the site survey, artwork supplied in the wrong format, a CMS specification written after the order — each one stops the clock and gives away the reserved production slot. Factories lose fewer weeks to machines than to unanswered emails.
Slip cause | When it surfaces | Evidence to demand | Who carries the cost |
Drawing approval delayed beyond the agreed window | Week 2–6 | A dated approval log with issue and return dates | Buyer — and the supplier is entitled to an extension of time |
Post-approval design change | Week 4–10 | Change-control form with cost and schedule impact priced before instruction | Buyer |
Non-stock extrusion die not ordered with the PO | Week 3–8 | Die order confirmation with the mill, dated | Shared, unless the die clause is silent |
Galvanising and coating queue at peak season | Week 6–12 | Named sub-supplier and a booked slot date | Supplier |
Chinese New Year shutdown | December–February | Shutdown and restart dates in writing, with the pre-holiday loading cut-off | Buyer, if the shipment was planned across it |
Vessel rollover in peak season | Week 10 onward | Booking confirmation with vessel name and cut-off, not a sailing estimate | Depends entirely on the incoterm |
Missing ISPM 15 mark or certificate of origin | At destination | Photograph of the mark and a copy of the certificate before loading | Buyer, unless the supplier arranged export clearance |
Two calendar facts rarely appear in a quotation. The Spring Festival shutdown removes three to four weeks of effective output, because a migrant workforce returns in stages rather than on day one; and the National Day holiday in early October removes a further week. Add the July-to-September typhoon season in Guangdong, which disrupts port operations rather than factories, and a well-planned programme has three obvious windows to avoid. Ask any bidder for their shutdown dates; a bidder who cannot supply them has not planned your shipment.

How do you write the schedule into the contract?
Put a dated milestone annex in the contract, define the approval clock, price delay with liquidated damages and define extension-of-time events exhaustively. Tie payment to factory acceptance testing rather than to calendar dates. Then name the incoterm and the insurance clause, because risk transfer and schedule responsibility part company at the ship's rail.
Clause | What it must say | Why it decides the outcome |
Schedule annex | Dated milestones per stage and per tranche, in calendar days | "Working days" across two countries with different public holidays is not a date |
Approval clock | A defined buyer response window, with a stop-the-clock rule | Without it, every late approval becomes an argument rather than a recorded event |
Liquidated damages | A rate per week of delay against the affected tranche, with a cap | Indicative market norm is 0.5% per week, capped at 5–10% of the tranche value; check what your own client imposes upstream |
Extension of time | An exhaustive list of buyer-caused events, with notice periods | An open-ended EOT clause cancels the damages clause above it |
Payment milestones | Deposit, pre-shipment instalment after FAT, balance against bill of lading | Paying on dates rather than events removes the supplier's incentive to test early |
Pre-shipment inspection | Ten working days' notice, buyer witness right, FAT report as a payment condition | The only point at which defects are still cheap to fix |
Incoterm and insurance | A named rule under Incoterms 2020 with a named port, and the cargo cover specified | CIF defaults to Institute Cargo Clauses (C); specify (A) if you need handling damage covered |
Shipping documents | Bill of lading, packing list with CBM and gross weight, commercial invoice, certificate of origin, ISPM 15 mark | A missing document at destination costs more than the freight it travelled with |
CIF deserves its own warning. The default cover under Incoterms 2020 is Institute Cargo Clauses (C), which responds to major casualties and not to the handling damage that shelters actually suffer. A scratched coated panel or a cracked tempered pane usually falls outside it. If the contract says CIF and nothing else, the buyer has insured the ship rather than the product.
【YEROO DATA NEEDED: standard payment terms and milestone structure, including the deposit percentage required to reserve a production slot and the documents released against each instalment】. 【YEROO DATA NEEDED: port of loading, sailing frequency and typical transit times to named destination ports, plus the policy on part-shipment and rollover】.
How do you score a supplier's schedule credibility?
Score the schedule, not the promise. A credible bidder produces bill-of-lading dates for previous projects against the dates originally promised, a capacity statement for your delivery month, named sub-suppliers for galvanising and glass, and a written approval turnaround. A bid without that evidence scores zero on the criterion that matters most.
Criterion | Weight | What earns full marks |
Dated delivery record | 25 | Three projects with promised date, actual B/L date and the variance explained |
Capacity at your delivery month | 20 | Monthly output stated in units, with the order-book load for that month |
Process control | 15 | Extrusion, galvanising, coating and glass either in-house or under a named, audited sub-supplier |
Approval turnaround | 15 | A written commitment in working days, with a named technical contact |
Transit plan | 15 | Named port pair, sailing frequency, and a stated rollover policy |
Contract posture | 10 | Accepts LD and defines EOT without rewriting either |
Set the pass mark at 70 out of 100 and treat a zero on the delivery record as an automatic fail, whatever the total. Then test the numbers you are given against the factory verification checklist before award, and cross-check the volume assumptions against the capacity analysis for 10, 100 and 500 unit orders. A schedule that has not been stress-tested against production capacity is a sales estimate.
YEROO's own record is checkable rather than asserted: 25 years of manufacturing in Foshan, a 31,000 m² facility and delivery to 109 countries, including a 26 m BRT structure for Laos shipped as spliced modules because no container and no galvanising bath takes a member that length in one piece.
What does a missed lead time actually cost?
A missed shelter date is rarely a shelter problem. It is a stop with no shelter, an installation crew on standby, a media contract that starts without a screen, and a port bill for a container nobody collected. The corrective cost runs from a few hundred pounds of storage to a lost advertising quarter.
Mistake | When it surfaces | Corrective cost |
Ordering a bespoke build twelve weeks before handover | Week 10, when the schedule is rebuilt | Air freight for controllers and glazing, or a delayed opening |
Approving drawings late and letting the production slot pass | Week 6 | Re-queueing behind existing orders, typically 3–4 weeks, at the factory's convenience rather than yours |
Scheduling a shipment across Spring Festival | January | Three to four weeks of lost output, or a pre-holiday vessel missed entirely |
Buying FOB without booking freight | Goods ready, no space | Origin storage, detention, and a peak-season rate on the replacement booking |
Accepting CIF with default Institute Cargo Clauses (C) | Damage discovered on site | A claim that covers the casualty but not the breakage, with the replacement panel on a new furnace run |
Delivering "as soon as ready" with no site storage | Two weeks early | Double handling, storage hire, and coating damage that becomes a warranty argument |
Container detained beyond free time | Day 8–15 after discharge | Per-day detention charges, indicative USD 100–250 per container per day, plus a re-delivery booking |
The cheapest correction is always the same: build the date backwards from handover, put the approval clock in writing, and refuse to let the production period stand in for the whole calendar. A buyer who knows that galvanising takes five to ten working days and that a vessel rolls in peak season can negotiate a realistic date — and a realistic date is the only one that survives contact with a site.
Common questions from buyers
How long does it really take from order to a shelter on site?Ten to fourteen weeks of production for a standard model, sixteen to twenty-two for a bespoke build, plus five to forty days of ocean transit depending on lane. Adding import clearance and inland delivery, plan on five to seven months from purchase order to a commissioned stop for a bespoke European project.
Does a custom shelter take much longer than a standard one?Yes, and not because fabrication is slower. A custom build adds an extra approval cycle, possibly a new extrusion die, a first article, and a full type-test of the delivered configuration. That is typically four to eight weeks before a single member is cut.
Can we pay more to shorten the lead time?Sometimes, within limits. Money buys queue priority, a second shift, and air freight for small components. It cannot compress a mill run, a galvanising bath, a furnace load or an ocean passage. Ask which stage the premium is buying; if the answer is "production", the saving is real.
Who is responsible when the vessel is delayed?Whoever holds the risk under the incoterm. FOB transfers risk at loading, so the delay belongs to the buyer. DAP and DDP keep it with the supplier until the named place. Choose the term by which party can actually influence the carrier, and state it in the contract rather than in the quotation.
Should the shelter be ordered before the foundations are built?Order in parallel, but release fabrication only after the foundation setting-out is approved. Foundations take four to six weeks including cure, and the installation sequence depends on the base plate positions matching the frame drawings. Parallel scheduling works; parallel guessing does not.
How much buffer should we add to a quoted lead time?Two weeks for a repeat order on a known lane, four weeks for a first order, a new supplier or a new port. Add the supplier's shutdown dates on top, then check the result against your opening date before you sign — not after.
A bus shelter lead time is three clocks, not one number. The factory clock runs ten to twenty-two weeks depending on how much of the design is new. The approval clock runs in your office and is the one most often allowed to overrun. The shipping clock belongs to a carrier who has never heard of your opening date.
Write all three into the contract. A dated milestone annex with calendar days, an approval window with a stop-the-clock rule, liquidated damages capped against the tranche, an exhaustive extension-of-time list, payment released against factory acceptance testing, and an incoterm whose insurance clause you have actually read. Then score bidders on B/L dates rather than promises, and treat shutdown dates as a pass-or-fail question.
YEROO supplies the schedule annex that goes with that contract: a dated production plan per stage, the compliance document set with verifiable certificate numbers, an itemised quotation split into unit, options, freight and spares, and a written statement of port, sailing frequency and transit time to your destination. Send your site list and required handover dates through the contact page and review the bus shelter range the plan is built against.